Tuesday 23 February 2010

Emails and change of plan Tuesday 23rd

  • ...................OK just like to Clarify.............original schedule.........

    o Week 1 07.01.10 Form group and decide idea
    o Week 2 14.01.10 Research/Story board and map
    o Week 3 21.01.10 Map/Storyboard/Research
    o Week 4 28.01.10 Modelling
    o Week 5 04.02.10 Modelling
    o Week 6 11.02.10 Modelling
    o Week 7 18.02.10 UV Mapping Texturing/Lighting
    o Week 8 25.02.10 Animating
    o Week 9 04.03.10 Rendering

    Week 8 - this week we are supposed to be animating and compositing......

    Because we are a week behind from the church being modeled this has effected the texturing and the lighting...not only that....texturing and UV mapping is taking longer then anticipated as Guy and Nath (allocators of task) are learning how to do this and is needing more time. In future 2/3 weeks need to be given to this task if we have other projects on the go at the same time.

    This is how we are doing according to schedule

    o Week 1 07.01.10 Form group and decide idea
    o Week 2 14.01.10 Research/Story board and map
    o Week 3 21.01.10 Map/Storyboard/Research
    o Week 4 28.01.10 Modelling
    o Week 5 04.02.10 Modelling
    o Week 6 11.02.10 Modelling
    o Week 7 18.02.10 UV Mapping Texturing/Lighting (modelling)
    o Week 8 25.02.10 Animating - we are still texturing and UV mapping
    o Week 9 04.03.10 Texturing and lighting Rendering

    So looking at this schedule if we were to schedule the project again this is more realistic....


    o Week 1 07.01.10 Form group and decide idea/ Research/Story board and map
    o Week 2 14.01.10 Map/Storyboard/Research
    o Week 3 21.01.10 Map/Storyboard/Research
    o Week 4 28.01.10 Modelling
    o Week 5 04.02.10 Modelling
    o Week 6 11.02.10 Animating/compositing
    o Week 7 18.02.10 UV Mapping Texturing/Lighting
    o Week 8 25.02.10 UV Mapping Texturing/Lighting
    o Week 9 04.03.10 Rendering

    However we lost a couple of weeks due to snow. But I think we should choose groups before the project starts. So we have as much time to spend on project and jobs.

    This is so tight for a 9 week project.

    This is a sharp learning curve as I can see where we need more time and perhaps not in others.